DataGraph placement

The DataGraphs can be undocked or floated from the bottom of the schedule. The floating DataGraph can be moved under, on, or above the schedule. Note that the DataGraph can cover task rows.

The DataGraphs  can also be displayed on the last page, only.

Float the DataGraphs:
  1. Choose Tools | Graph Options | Setup DataGraph.

  2. Floating DataGraph. (This option is found at the bottom of the dialog box).

Display the DataGraphs on the last page, only:
  1. Choose Tools | Graph Options | Setup DataGraph.

  2. Floating DataGraph.

  3. Show DataGraphs on last page Only.

Move or re-size floating DataGraphs:

Floating DataGraphs cannot be moved to the left or right, but they can be moved up and down. The width is fixed, but the height can be adjusted.

  1. Click the arrow tool in the toolbox.
  2. To move the DataGraph, hover to cursor over the DataGraph frame. The cursor changes to a four-arrows cursor. Click and drag to move the DataGraph.
  3. To re-size the DataGraph, hover the cursor over a corner of the DataGraph frame or at the midpoint along the top or bottom of an edge. Click and drag to re-size the DataGraph.
Overlay ValueSets from a single DataGraph
  1. Right click the DataGraph and choose Properties.
  2.  Plot ValueSets and Y-Axis in Schedule Area...
Overlay ValueSets from multiple DataGraphs:
  1. Right click a DataGraph and choose Properties.
  2. Click the tab for DataGraph1.
  3.  Overlay ValueSets from DataGraph2 (if those ValueSets are desired.)
  4.  Overlay ValueSets from DataGraph3 (if those ValueSets are desired.)
Hide the y-axis for a DataGraph which is no longer needed:

If a schedule displays the y-axis but no values are displayed, it's possible the schedule was originally set up with a DataGraph but now does not include one.  Hide the y-axis:

  1. On the Tools tab, choose Graph Options | Setup DataGraphs.
  2. Show This Graph for whichever Datagraph has this option checked:  Plot ValueSets and Y-Axis in Schedule Area...

 

 

Related Topics

  1. Track and graph numbers
  2. Create and change DataGraphs
  3. Currency display in DataGraphs
  4. DataGraph on top of the schedule area
  5. DataGraphs overview

 

  

Guided Help Home

 

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.